- Discover Clarksville Tennessee - https://www.discoverclarksville.com/articles -

Clarksville Downtown Transit Center reopens

Clarksville Transit SystemClarksville, TN – Clarksville Transit System (CTS) has reopened its downtown Transit Center on Legion Street after an eight-month renovation project was completed last week.

Paul Nelson, Clarksville Transit System Director, said CTS will host a reopening celebration from 10:00am to 2:00pm on Friday, December 20th, 2019. CTS officials will be on hand to greet the public, offer snacks and soft drinks and CTS merchandise.

The renovated Clarksville Downtown Transit Center has a new, wider walkway and newly paved bus lanes. [1]

The renovated Clarksville Downtown Transit Center has a new, wider walkway and newly paved bus lanes.

The Transit Center project improved the look, comfort and functionality of the building and surrounding area.

The work included a new roof, and new paint, wallpaper and flooring inside the building. Outside, the bus terminal got new paving, sidewalk repairs, additional ramps and seating, and new landscaping.

Related work on the Transit Center Parking Garage — including concrete repair, reinforcement of steel beams, tuck pointing, and brick and lintel replacement — was completed in October.

The overall project cost $1.2 million and was funded primarily through grants, with 90% coming from Federal and State sources, and 10% from the City.

Inside, the Clarksville Downtown Transit Center has new seating, new flooring and lighting, and a fresh new look. [2]

Inside, the Clarksville Downtown Transit Center has new seating, new flooring and lighting, and a fresh new look.

Transit Center work began April 22nd, and the contract close-out date was December 2nd. During construction, the ticket office was moved across the street to the Downtown Commons, and passengers accessed buses on Legion Street.

Here are the major elements of the Transit Center renovation:

[320right]CTS had hoped contractors would complete the renovations by October 1st, but the project was delayed when it was discovered that the weight on the Transit Center structure may be excessive.

The project initially called for replacing paving materials pound for pound, but the design was changed to reduce the weight by replacing poured-in-place concrete with block, and eliminating dirt and rock fill by using light-weight geo foam and other lighter materials.

Extra time was needed to make the weight-related design decisions and changes, but otherwise the project remained on schedule.